9:35am- Excavating to set pull boxes and place conduit inside boxes
  
11:13am- Pour concrete for curb and gutter heading South on Pine towards Madison. 
11:23am- Finish pouring concrete sidewalk in between drives at the church parking lot on Jefferson.
 
2:48pm- Excavated for the City of Strafford, so they can relocate a service on Pine at station 3+22.66
 
3:48- Set curb stops on the West side of the church parking lot and drove pins in to retain in place.
 
 
 