Monday, April 24, 2017

Strafford sidewalk

 
8:29am- Forming on the Southeast corner of Jefferson and Pine for curb and gutter.
 
8:40am- Forming for sidewalk on the Southwest corner of Pine and Jefferson 
  
11:08am- Set and compacted base rock for sidewalk concrete pour. Also built forms for ADA ramp.
  
 
12:20pm- First pour of the day Southwest and Southeast corners of Jefferson and Pine. Built 2 ADA Ramps and set 3 truncated domes   
 
 
3:10pm- Forming the Northeast corner of  Pine and Jefferson 
 
3:55pm- Continue to excavate on the Southeast corner of Jefferson and Pine for sidewalk.
5:08pm- Compacting base for tomorrow's pour, on the Southeast side of Jefferson and Pine.
 