11:19am- Installing handicap signs on Pine Street
3467 City of Strafford Sidewalk
Tuesday, June 20, 2017
Thursday, June 15, 2017
Strafford sidewalk
8:12am- Pouring 10' sidewalk on the Northeast corner of S Madison and Pine. Placed ADA Detectable warning mat .
Tuesday, May 23, 2017
Strafford sidewalk
8:04am- Applying asphalt across Pine Street where 2" conduit was placed for future.
9:53am-Applied asphalt in several areas of the job site to match existing grade from the road.
Monday, May 22, 2017
Strafford sidewalk
7:21am- Built mail box frame.
7:12am- Storm drain and pipe installed at the Northeast corner of Pine and S Madison
7:49am- Formed and poured the ADA ramp on the South East corner of Pine and S Madison
8:02am- Formed and poured for curb and gutter at the Northeast corner of Pine and S Madison
9:09am- Relocated mail boxes
Thursday, May 18, 2017
Strafford sidewalk
7:36am- Painted edges of handicap ramps
7:55am Continue to excavate the North East corner of Pine and S Madison
10:07am- Cleaning the corners up. Prepping for asphalt.
Wednesday, May 17, 2017
Strafford sidewalk
8:31am - Set galvanized metal tread plates on the South West corner of Jefferson and Pine formed and poured concrete.
8:46am- Poured concrete at station 1+00 on Pine Street for the ADA approach ramp.
10:09am- Finished forming for tread plates on the South East corner of South Madison and Pine. Poured concrete to set in place.
12:08pm- Started to excavate on the North East corner of Pine and S Madison
3:08pm- Placed 40' of CMP for the new drain box on the North East corner of Pine and S Madison
Tuesday, May 16, 2017
Strafford sidewalk
9:20am- Prepping the ground for seeding and mulching
10:48am- Starting to excavate the Northeast corner of Pine and S Madison