7:58am- Excavating church parking lot for sidewalk installation
9:47am Continue to excavate church parking lot headed north towards Chestnut and compacting base for concrete.
12:01pm- Excavating existing sidewalk and curb on Pine. Heading west towards S Madison
1:33pm- Pouring concrete for sidewalk through church parking lot, heading South on Jefferson.
2:15pm- Continue to excavate existing curb and sidewalk on pine heading east towards South Madison.
5:00pm- Final product