Monday, May 8, 2017

Strafford sidewalk


7:47- Excavating at the west end of Pine St in front of Common Grounds Cafe 
 
9:37am- Building forms for front door step and ramp

10:21am- Continue to excavate at the corner of South Madison and Pine
 
12:01pm- Raised two clean outs and installed a pull box on the corner of S Madison and Pine.

1:13pm- Poured front step, ramp, curb and gutter at the corner of  S Madison and pine.
   