7:54am- Prepping ground and compacting base for concrete pour at stations 1+02.39 - 0+60.90 on Pine St.
9.32am- First pour for the day in between stations1+02.30 to 0+60.90 on Pine St.
10:26am- Cutting asphalt to place 2" conduit for future electric.