9:00am- Excavating for drainage pipe, heading West on Pine from Jefferson
11:25am- Placed the remainder of concrete on the North end of Madison and working to finish South to Pine.
1:57pm- Truncated dome set in place on the North end of Madison
3:36pm- Crew installed 100' of HDPP 15" pipe headed West on Pine from Jefferson