Thursday, March 2, 2017

Strafford sidewalk

 
8:15am- Contractor Excavating driveways and forming for sidewalk pour. Heading South on Madison.
 
8:43am- Drainage pipe delivery
 
10:00am- Placing more base in preparation for tomorrow's concrete pour
 
4:00pm- Excavating on South Jefferson for installation of drainage pipe.
  
5:20pm- Installed 80' of HDPP  18" pipe  on Jefferson  in between Pine and Old Route 66
 