7:59am- First pour of the day South East drive on pine and the curb and gutter on the South West corner of Jefferson and Pine.
8:39am- Removed head walls from Southeast and Northeast corners of Jefferson and Pine.
10:03am Set third pull box and light base
12:25pm- Second pour of the day Southeast drive on Pine, curb and gutter at the Southwest corner of Pine and Jefferson.
1:53pm- Excavating West on Pine setting 2" conduit for future street lights.
3:18pm- Continue to excavate on pine headed west towards Madison
4:09pm- Building forms for 5x5 ramps and front doorway steps
5:04pm- Excavating for another light pole base and pull box