Tuesday, February 28, 2017

Strafford sidewalk

8:00am- Sidewalk removal begins on Madison street heading South towards Pine.
 9:50am- Continue to excavate South on Madison toward Pine. 
12:42pm- Applying base prior to concrete application.
 
3:56pm- Finish day off, excavated 556.4 feet of sidewalk on Madison and placing silt sock
 
 